servicesabout usgallerynewscontactus

07.06.07 - NEW PROJECTS
Recently received orders

07.06.07 - ONGOING PROJECTS
Our current ongoing projects

07.06.07 - RECENT PROJECTS News of our recent projects

01.07.06 - SAMPLING PLATFORMS ON CHIMNEYS
Environmental Agency published new Technical Guidance

01.07.06 - ATLAS REALISING POSSIBLE DANGERS TO OPERATIVES
when fitting or inspecting chimneys

 

NEW PROJECTS

1. The inspection of a 60m chimney, in a remote part of the Sind Province in Pakistan, which serves as a vent for sour gases at a gas collection and pumping station. The original chimney was designed, manufactured and erected by F E Beaumont Ltd in 1992 and since then we have sent operatives on two previous occasions to inspect it.

2. The preparation of a report on the condition of a steel chimney, the remedial works required to refurbish it and undertake the design for the fitting of an additional 2no inlets

3. The recommended remedial works to the chimney we inspected last year for Edenderry Power Operations Ltd, Co Offaly, Eire.

4. The supply and fitting of architecturally designed perforated cladding to 2no structures, containing flues serving generators, at a central internet hub / access facility in London.

5. The erection of steelwork which will provide a modern training facility for Wiltshire Fire Services at their Swindon Fire Station.

6. To prepare a report on a hospital chimney where a split in the steel windshield as been discovered.

RECENT PROJECTS

1. Flues gas calculations for Zisman Bowyer and Partners.

2. Inspection of a 70m high steel chimney for Edenderry Power Operations Ltd, Co Offaly, Eire.

3. Demolition of existing flues and supply and installation of new, for Dalkia Energy and Technical Services.

4. Inspection of a 52 multiflue chimney for Thames Water Utilities.

5. Inspection works to liners within a concrete chimney at a hospital in Taunton, Somerset where the client wanted to install a new boiler and connect it to an unused steel liner. After an ultra-sonic inspection it was found that the disused liner appeared to have corrosion problems over the top section and further works were undertaken to discover the cause and extent of the problem. The problem was localised to an area under and around an inspection door which was badly fitted and allowing the ingress of moisture which held by the mineral wool insulation had caused the steel surface to corrode. The corrosion was not severe and a report was submitted recommending that a new door of a better design be fitted, the corroded areas mechanically cleaned and painted and new insulation fitted.

5. The design, manufacture and erection of a 27m high mast to take 3no 600mm diameter twin wall flues for a new boiler house at the famous Great Ormond Street Hospital for Children. The mast was located in a courtyard and so the required telescopic crane had to stand out in the roadway. Because the area is very busy and congested a road closure was required and the work was completed on the last Saturday in March this year.

6. Pilkington Ltd were looking at changing a process which was exhausted via a brick lined steel chimney at a plant in Australia and technical advice was presented on the viability of carrying out the modifications the client was considering.

ONGOING PROJECTS

1. Design study and the supply of a tuned mass damper and steelwork for upgrading a chimney originally built in 1982 to the current British Standard.

2. 11m high Cor-Ten multiflue chimney and flues for the energy centre Lennoxlove House, Haddington near Edinburgh. Home to the Duke of Hamilton.

3. The demolition of an 18m chimney, originally provided by F E Beaumont Ltd in 1971, and associated flue run. The chimney is in a very poor condition with a hole visible in the structural shell, extremely thin steel in places and corroded holding down bolts. New holding down bolts will be drilled and resin bonded into the existing concrete base prior to the replacement chimney and flue being erected.

4. The removal of 4no twin wall chimneys from boilers mounted on the roof of the Grovesnor House Hotel on Hyde Park, London.

PAST PROJECTS INCLUDE

1. In the early 1980’s F E Beaumont Ltd supplied a 60m high chimney, in the North West of England, containing a single small diameter liner which was to vent gasses when tankers were unloading. The client needed to upgrade the plant and required a larger vent to be fitted so Beaumont’s undertook a design study to assess the condition of the chimney and what works were required to bring it inline with the current BS4076:1989 Specification for Steel Chimneys. It was found that by removing the existing helical stabilisers, fitting a tuned mass damper and fitting strengthening plates and re-bolting at flange levels the chimney could be refurbished to meet the current standard. Beaumont Technical Services Ltd is providing the tuned mass damper and additional steelwork for others to fit.

2. Home to the Duke of Hamilton, Lennoxlove House is undergoing a major refurbishment and the project includes a new energy centre with 3no boilers. Beaumont Technical Services Ltd have been contracted to design, supply and install an 11m high multiflue chimney with a Cor-Ten windshield and the ducting between the boilers and chimneys.

3. When Zisman Bowyer and Partners were looking at a project with regard to larger boilers, than originally envisaged, having been connected to liners in an existing multiflue chimney they can to us to perform the calculations relating to the expected resistances and velocities that would be encountered. Within three days they had the calculations for both gas and oil firing at full load and in turndown mode.

4. When originally built in the early 90’s the Edenderry Power Plant was reputed to be the largest peat burning plant of its type and the 70m high insulated and clad chimney was originally designed, manufactured and erected by F E Beaumont Ltd. In the late summer of this year the chimney was inspected both internally and externally and an extensive report complete with photographs and recommended remedial works presented to the client.

5. When it was found that the flues on a boiler system, serving a home for the elderly in Greenwich, London, were holed and in very poor condition Dalkia Energy and Technical Services contacted us with regard to the replacement. The existing steel flues were demolished, a plenum box refurbished and new twin wall flues installed. With the fitting of a temporary flue/chimney to serve one of the boilers the residents were never without heating or hot water during the works.

6. In keeping with the clients regular inspection schedule a 52m high multiflue chimney at the Bacton Sludge Incineration Plant was inspected during a partial shut-down. The chimney originally was designed, built and erected by F E Beaumont Ltd and is unusual as the tuned mass damper is ‘Y’ shaped and fitted within the windshield avoiding the liners.

SAMPLING PLATFORMS ON CHIMNEYS

Since sampling of flue gases has increased and the Environmental Agency published Technical Guidance Notice M1 Sampling Requirements for Monitoring Stack Emissions to air from Industrial Installations which meant that sampling platforms, where fitted, became far larger the writer has been extremely concerned with the safety aspects especially when retro-fitted, and voiced his concerns at ATLAS (Association of Technical Lightning and Access Specialists) meetings.

ATLAS REALISING POSSIBLE DANGERS TO OPERATIVES

ATLAS realising the possible dangers to their operatives, when fitting or inspecting chimneys, to which those platforms and access had been fitted, decided to bring this to the Public Notice and started a campaign to this end. A series of articles and letters appeared in Contract Journal and following this the Environmental Agency, ATLAS and Source Testing Association had a very productive meeting and the EA took on board all that ATLAS said and a revised edition of TGN M1 should hopefully be published this summer.

It is surprising how many platforms and access ladders have been fitted to chimneys without a structural analysis being undertaken to ensure that the additional forces can be accommodated by the original and in the view of the writer it is only a matter of time before there is a catastrophic failure due to an owner/operator not realising this. Most chimneys have been designed with little additional capacity to allowable stresses, a matter of design being maximised against cost.

For more information as to whether a sampling platform is required,
it is surprising how often sampling can be undertaken in the flue run, contact Dave Curtis of the Source Testing Association at
dave.curtis@s-t-a.org

If you require a structural analysis of your chimney to check that it can accept the imposed loads of ladders and platforms complete the consultation form on the contact us page.

home » services » about us » gallery » news » contact us